NOTICE FOR OPEN TENDER (ITB)-Upgrading of Bossaso Airport, Puntland, Somalia

Recommended Posts

Carafaat   

UNOPS is funding the upgrading of the Airport? That is quite unique, most of these UN agencies are worthless and hardly fund infrastructural projects. I don't how Faroole pulled this off, but it definitely deserves appraisal for actually getting the UN to fund something relevant.

Share this post


Link to post
Share on other sites
YoniZ   

Carafaat;976670 wrote:
UNOPS is funding the upgrading of the Airport? That is quite unique, most of these UN agencies are worthless and hardly fund infrastructural projects. I don't how Faroole pulled this off, but it definitely deserves appraisal for actually getting the UN to fund something relevant.

It is a smart move, even though UNOPS is the implementing agency, the Italian government, and to a lesser extent Puntland government are the funding bodies. That airport never lacked suitable funders, every time the deal breaker was who gonna implement the project.

 

I wonder if Nomad knowledgeable in these kind of projects can shun a light what sort of Airport this will be after completion (if done according to the plan).

 

Below is the TECHNICAL DESIGNS AND DRAWINGS Document:

 

http://www.unops.org/ApplyBO/File.aspx/10.%20ITB-KEOC-2013-012%20-%20Section%20IX%20-%20Drawings.pdf?AttachmentID=75827f59-6b8c-4613-8d70-36fb2bc57c6d

Share this post


Link to post
Share on other sites

nothing is this transparent.

 

either this is a formality because the contractor has already been chosen or it's a gimmick.

 

judging by PL's ability to ''shock and awe''. i don't know what to think.

Share this post


Link to post
Share on other sites
Somalia   

EXTENT OF CONTRACT

 

The works include construction of;

1. 2650m long by 45.0m wide runway including 3No. turn pads (1 at each end and 1 at the middle);

2. 191m long by 18m wide taxiway;

3. 167m long by 106m wide apron around the existing pads;

4. 250mm of natural gravel on widened and extended sections;

5. 230mm lean concrete as base course for the runway and taxiway;

6. 70mm of Marshall Asphalt binder course for the runway and taxiway;

7. 50mm Marshall Asphaltic Surface course for the runway and taxiway;

8. 340mm granular base for apron;

9. 260mm rigid pavement for apron;

10. 7.5m wide gravel shoulders on each side runway (600mm in thickness);

11. 3.5m wide gravel shoulder on each side of the taxiway (600mm in thickness);

12. A total of 330m long by 90m wide Runway End Safety Areas (600mm in thickness), and;

13. Runway, taxiway and apron surface makings and signs.

 

Others include;

 

14. Construction of 1No. new 2.0mx1.0mx150m box concrete box culvert;

15. Construction of a chain link perimeter fence of length totaling about 9,100m;

16. 2No. security gates;

17. Rehabilitation and extension of a cut-off drain along the upper side of the runway, and;

18. Stone pitching in selected areas.

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Sign in to follow this